The proposed schedule for the bidding process is below – Please follow the Revised Dates. On January 18, 2024, DOER and the Distribution Companies made a joint Informational Filing at the DPU to notify the Department that they are extending the Bid Submission Date and subsequent solicitation schedule dates for the 83C Round IV solicitation. Please see the Informational Filing on the Round IV Documents page.

Any changes to the schedule up to and including the due date for submission of proposals will be posted at the Distribution Companies website, MACleanEnergy.com. The Evaluation Team reserves the right to revise the schedule as necessary. In addition, the Evaluation Team reserves the right to establish a schedule that is different than the one set forth in this RFP.

EventOriginal RFP DatesRevised Dates
Issue RFPAugust 30, 2023August 30, 2023
Bidders ConferenceOctober 5, 2023October 5, 2023
Deadline for Submission of QuestionsOctober 17, 2023October 17, 2023
Due Date for Submission of Confidential and Public ProposalsJanuary 31, 2024 at 12:00 (noon) EDTMarch 27, 2024 at 12:00 (noon) EDT
Selection of Projects/Commence NegotiationsJune 12, 2024August 7, 2024
Execute Long Term Contracts and MOU with DOERAugust 14, 2024October 9, 2024
Submit Long Term Contracts for DPU ApprovalSeptember 18, 2024November 13, 2024